4月20日,中國十五冶富邦銅業項目順利實現“4·20”通水通電目標,為項目聯試聯調提供堅實保障。
據悉,綜合(he)管(guan)網埋地(di)管(guan)道共計約8000米,通(tong)水(shui)(shui)(shui)前,項目部(bu)提前完成關(guan)鍵(jian)線路管(guan)道試(shi)壓(ya)工作,20號當天,高位水(shui)(shui)(shui)池(chi)(chi)采用生產水(shui)(shui)(shui)、軟化水(shui)(shui)(shui)埋地(di)管(guan)成功為熔(rong)(rong)煉循(xun)(xun)環(huan)水(shui)(shui)(shui)水(shui)(shui)(shui)池(chi)(chi)、制(zhi)氧循(xun)(xun)環(huan)水(shui)(shui)(shui)水(shui)(shui)(shui)池(chi)(chi)注水(shui)(shui)(shui)。在(zai)2號10千伏(fu)配電室1AH0506E11和2AH0506E10柜真空斷路器先后合(he)閘,在(zai)10千伏(fu)線路、高壓(ya)負荷隔離(li)柜和干式(shi)(shi)變壓(ya)器3次沖擊試(shi)驗合(he)格后,熔(rong)(rong)煉循(xun)(xun)環(huan)水(shui)(shui)(shui)配電室正式(shi)(shi)通(tong)電。